PLANNING FACTORS
    Planning considerations
Expansion drivers
Customer needs
Planning criteria
System performance criteria
Capacity ben. margin criteria
Transmission reserve margin
Facility rating criteria
Model building criteria
Facility condition criteria
Planning zones
System alternatives
Load forecast criteria
Economic criteria
Environmental criteria
Variations on ATC criteria
Other considerations
Methodology & assumptions
Prioritization
NERC compliance
  RELATED RESOURCES
 
Planning Zones
FACILITY CONDITION CRITERIA PDF of Current Page
 

The facility condition criteria to be utilized by ATC for system planning purposes will include:

  1. Any transmission line on structures that are beyond their design life, any transmission line that has exhibited below-average availability or any transmission line that has required above-average maintenance will be considered a candidate for replacement. In assessing potential line replacements, consideration will be given to other needs in the area of the candidate line to determine whether rebuilding the line to a higher voltage would fit into the “umbrella” plan for that planning zone (see Planning Zones). ATC engineering, operation and maintenance and environmental employees work together to coordinate such assessments.
  1. Any substation bus that is beyond its design life, has exhibited below-average availability, or has required above-average maintenance will be considered a candidate for rebuilding and potential redesign. In assessing potential bus rebuilds, consideration will be given to likely and potential expansion at candidate substations, including consideration of the “umbrella” plan for the planning zone. ATC engineering, operation and maintenance and environmental employees work together to coordinate such assessments.
  1. Any substation whose design or configuration prevents maintenance in a safe manner on substation equipment or lines terminating at the substation will be considered a candidate for rebuilding and/or potential redesign/reconfiguration. In assessing such rebuilds/redesigns/reconfigurations, consideration will be given to likely and potential expansion at candidate substations, including consideration of the “umbrella” plan for the planning zone. ATC engineering, operation and maintenance and environmental employees work together to coordinate such assessments.
  1. Any underground cable that is beyond its design life, has exhibited below-average availability, or has required above-average maintenance will be considered a candidate for replacement. In assessing potential cable replacements, consideration will be given to other needs in the area of the candidate cable to determine whether replacing the cable with a cable with a higher ampacity or with a cable capable of a higher voltage would fit into the “umbrella” plan for that planning zone. ATC engineering, operation and maintenance and environmental employees work together to coordinate such assessments.

 