PLANNING FACTORS
    Planning considerations
Expansion drivers
Customer needs
Planning criteria
System performance criteria
Capacity ben. margin criteria
Transmission reserve margin
Facility rating criteria
Model building criteria
Facility condition criteria
Planning zones
System alternatives
Load forecast criteria
Economic criteria
Environmental criteria
Variations on ATC criteria
Other considerations
Methodology & assumptions
Prioritization
NERC compliance
 
FACILITY RATING CRITERIA PDF of Current Page
 

The following ATC Operating Instructions provide documentation of ATC’s facility ratings criteria. This methodology has been updated since publication of the 2011
10-Year Assessment:

1) PR-0285 Facility Ratings Update and Application

2) CR-0061 Conductor Ampacity Ratings for Overhead Transmission Lines

3) CR-0063 Substation Equipment Ampacity Ratings

4) CR-0062 Ampacity Ratings of Underground Transmission Lines

 

We will actively review, replace, and document legacy ratings with ratings based upon ATC criteria in our Substation Equipment and Line Database (SELD). The legacy ratings from the previous transmission facilities owner’s planning and operations models will be used in ATC planning models until valid SELD ratings, which are consistent with ATC facility rating criteria become available. The facility ratings criteria for legacy ratings are those of the corresponding contributing utility (e.g. Alliant East, Madison Gas & Electric, Upper Peninsula Power, Wisconsin Public Service, and We Energies). The ATC facility ratings criteria are consistently applied among ATC Planning, Engineering and Operations.

 

Facilities to be considered include, but are not limited to – overhead line conductors, underground cable, bus conductors, transformers, autotransformers, circuit breakers, disconnect switches, series and shunt reactive elements, VAR compensators, current transformers, wave traps, jumpers, meters, and relays (both overcurrent/directional overcurrent/impedance settings and thermal limits). Ratings derived from the ATC facility rating criteria are to be consistent with the following NERC standard.

(Applicable NERC Standards: FAC-008-1-R1)


 
Copyright 2011 American Transmission Company. All Rights Reserved