PLANNING FACTORS
    Planning considerations
Expansion drivers
Customer needs
Planning criteria
Methodology & assumptions
Prioritization
NERC compliance
  RELATED RESOURCES
 
Generation Interconnections
Zones & study results
Projects
Planning criteria
Routing & Siting
Table PF-1 -- Projects in 2012 analysis
Table PF-2 -- Projects in 2016 analysis
Table PF-3 -- Projects in 2021 analysis
Table PF-4 -- Projects in 2026 analysis
Figure PR-9 -- Generation Interconnection requests
 
METHODOLOGY & ASSUMPTIONS PDF of Current Page
 

Overview

This section describes the methods and techniques that we use to analyze our network transmission system for this assessment. Economic, regional, environmental and asset management planning processes are covered on other sections of this Web site.

As part of the network assessment, ATC conducted power flow analyses to identify problems or constraints on the transmission system and evaluated the merits of potential reinforcements to address the system limitations that were identified. Once these analyses are complete, ATC meets with our stakeholders to discuss the preliminary results.

ATC’s network planning process is summarized in the below figure:

Included in this section is a discussion of which years ATC identified to model to satisfy both the near-term (1 – 5 year horizon) and long-term (5 year and beyond horizon) NERC standards for assessing the transmission system.  Also included in this section is discussion on how ATC built each of the models used in this assessment. Discussion items include topics such as load forecasting, which reinforcements and new generation to include in models, which system load levels, import levels and system bias scenarios to evaluate.   

 

During the network assessment of our transmission system, we performed simulations on a variety of models as discussed below in this section.  ATC not only uses these models to identify where constraints or system limitations may exist, but we also use these models in testing the robustness of potential system reinforcements.  Per our Planning criteria, constraints or system limitations are identified for NERC Category A type system conditions when bus voltages drop below 95 percent or exceed 105 percent of their nominal voltage or when any system element exceeds it normal rating for the appropriate seasonal model. For NERC Category A or system intact conditions, ATC’s Planning criteria also requires for generators to be limited to 90 percent of their maximum reactive power capability within ATC’s footprint.

 

For NERC Category B, C or D contingencies, system limitations or constraints are identified using slightly different criterion.  For these types of system contingency conditions, ATC’s Planning Criteria identify system limitations when bus voltages drop below 90 percent or exceed 110 percent of their nominal voltage or when any system element exceeds its emergency rating for the appropriate seasonal model.  For these three NERC categories, ATC’s Planning Criteria requires generators to be limited to 95 percent of their maximum reactive power capability within ATC’s footprint. Exceptions to the voltage range criteria apply for certain interconnected entities, and are evaluated in accordance to their signed interconnection agreements.  Voltage range exceptions also apply to underground and underwater cables.

 

The analyses conducted in this transmission system assessment included steady state power flow analyses, stability simulations, multiple outage impacts as well as economic evaluations, generator interconnection impacts, transmission-distribution interconnection impacts and environmental assessment impacts.

 

Network assessment methodology

American Transmission Co.’s 2011 10-Year Transmission System Assessment provides current results of planning activities and analyses of the company’s transmission facilities. These activities and analyses identify needs for network transmission system enhancement and potential projects responsive to those needs.

Since 2001, we have engaged in open and collaborative efforts to share information and solicit input on our plans. We believe that in making our planning efforts transparent and available to the public, the proposals for needed facilities can be more readily understood and accepted by communities that stand to benefit from them. In recent years the federal government has taken additional steps to ensure that transmission-owning utilities have produced and shared planning information with the public and local stakeholders.

The information in this report provides further foundation for continued public discussions on the transmission planning process, identified transmission needs and limitations, possible resolutions to those needs and coordination with other public infrastructure planning processes.

Computer simulation model years for the 2011 network Assessment analyses were selected in order to meet NERC requirements for a 1-5 year horizon and beyond the 5 year horizon. The years 2012 and 2016 were selected to meet the 1-5 year horizon. The years 2021 and 2026 meet the beyond 5 year horizon. A range of system conditions and study years were developed and analyzed for the 2011 Assessment. Steady state peak load models for all four years were created. In order to determine how close ATC generators were to their maximum reactive power output, two additional models were created for each year. The first model for each year studied reduced ATC generator maximum reactive power by 10 percent. These models were utilized to determine generator reactive power output under intact system conditions (TPL-001-0). A second model for each year was created with net maximum reactive power capability reduced by 5 percent. These models were used for our N-1 (TPL-002-0) analysis.

The needs identified in this Assessment were determined by identifying facilities whose normal or emergency limits are exceeded. The criterion we use to determine what these limits should be is provided in Planning criteria).

This 2011 network Assessment was developed in a chronological fashion. Planned transmission additions expected to be in service by June 2012 were included in the 2012 model, as listed in Table PF-1. Projects for which we have completed our analysis and are either under construction, have filed an application to construct, or are in the process of preparing an application were included in the 2016, 2021 and 2026 models as appropriate based on projected in service dates (See Tables PF-2, PF-3 and PF-4).

 

Load forecast

Steady state summer peak models are built using our customers’ load forecasts (50/50 projections) as a starting point, meaning that there is a 50 percent chance that the load level will either fall below or exceed the customer projection. Customer load forecasts were gathered for all ATC customers through the year 2020 (and in some cases 2021/2026).  The forecasts were compared to previous historical and forecasted data to ensure validity and consistency. As a final step, the finalized forecast information was forwarded back to our individual customers to ensure their concurrence.  Once consensus was achieved, the data was incorporated into our models.

 

Certain ATC customers did not provide an 11th-year load forecast for the year 2021. To obtain a forecast for 2021, certain customer-provided forecasts were extended by growing their load by using a 3-year linear growth rate calculated over the last three years of the forecasts provided by the customer. Load power factors were held at their 2020 levels. Non-scalable loads were also held at their 2020 levels using this methodology.

 

The 2026 summer peak load model was developed utilizing similar methodology. To obtain a projection for 2026, customer-provided forecasts were extended by growing their load by using a 3-year linear growth rate calculated over the last three years of the forecasts provided by the customer. Load power factors were held at their 2020 (or 2021) levels. Non-scalable loads were once again held at their 2020 (or 2021) load levels. It should be noted that the loads utilized in the 2026 summer peak model do not reflect an actual load forecast, but merely a projection (or “load model”) based upon the best available information. The purpose for the 2026 projection is not to develop projects to address all issues, but to develop a sense for the need(s) for long lead-time projects.

 

ATC Peak Load Projections (MW) including line losses

Year

MW load

Compounded growth rate

2011

13,111

N/A

2012

13,258

N/A

2016

13,805

1.02% (2012-2016)

2021

14,531

1.03% (2016-2021)

2026

15,292*

1.03% (2021-2026)

Overall

 

1.03% (2011-2026)

*load model, not a load forecast

 

It should be noted that we worked with the distribution companies as much as possible to confirm forecast variations from past trends. In a few cases we revised power factors to reasonable levels to prevent creating expensive transmission projects for voltage support. In most cases these issues would ultimately be solved through distribution system power factor correction. ATC will be in ongoing discussions with our customers to determine the best plan for these situations.

Model building

Assumptions common to all models

The following assumptions are common to all models studied in the 10-Year Assessment.  Any exceptions are listed within the respective assumption section:

  • New Generation
  • Generation Retirements
  • Cuttoff dates
  • Generation Project Schedule
  • Generation outside of the System
  • Generation Dispatch
  • Line and Equipment ratings
  • Project Criteria

New generation     

There have been numerous generation projects proposed within ATC’s service territory. Many of these proposed projects have interconnection studies completed and a few have had transmission service facility studies completed. Several have proceeded to or through the licensing phase and several more are under construction. However, there are numerous proposed generation projects that have dropped out of the generation queue (refer to Generation interconnections), adding considerable uncertainty to the transmission planning process. To address this planning uncertainty, we have adopted a criterion for purposes of this and prior Assessments, to establish which proposed generation projects would be included in the 2011 Assessment models.

 

Previously (before the advent of the MISO Day 2 market) the criterion was that those generation projects for which, at the time the models were developed,

  1. ATC had completed a generation interconnection impact study, a generation interconnection facility study, a transmission service impact study and a transmission service facility study, and
  2. the generation developer or a customer of the developer had accepted the transmission service approved by ATC.

In the 2011 10-Year Assessment, the criterion was broken into two time frames, years 1 through 5 and 6+ years.

  1. For years 1 through 5, only those generators with FERC approved interconnection agreements will be included in the planning models.
  2. Beginning with year 6 and continuing into the future, generators are only required to have a Facility Study completed in order to be included in the 10-Year Assessment models.

A number of wind generators in the ATC footprint have suspended FERC approved interconnection agreements. For the first three years following their requested in-service dates, ATC criterion calls for modeling these facilities but dispatching them at the bottom of the dispatch order. After the three years, the generators will be dispatched in their normal dispatch order. The wind generators with suspended agreements were included in the models built for the 10-Year Assessment analysis. The 2011 and 2012 models showed these generators as out of service. The 2016 and 2021 models should have had these generators in-service and dispatched.


Generation retirements

On occasion, generators connected to the ATC transmission system are retired or mothballed. As a result, we developed criteria to determine when generators should no longer be included in our 10-Year Assessment models. If the generator has a completed MISO Attachment Y study, the generator will be disconnected in the appropriate load flow study models. In addition, ATC sent an annual letter to each generation owner. Generating companies were asked to identify generator retirements or mothballing that should be included in ATC’s planning horizon. Generators identified as such by the customer will be modeled off line in the relevant models.

 

There are generators that have been publicly announced as likely candidates for retirement. However, using the disconnection criteria above, in the 2011 10-Year Assessment models we assumed the following generators were to be out of service:


Plant Name

Zone

Installed capacity

Assumed out of service

Rock River 1

3

71 MW

Jan 2011

Rock River 2

3

 75 MW

Jan 2011

Blackhawk 3

3

24 MW

Jan 2011

Blackhawk 4

3

25 MW

Jan 2011

Blount 3

3

39 MW

Jan 2013

Blount 4

3

 22 MW

Jan 2013

Blount 5

3

28 MW

Jan 2013

 

 

 

 

Net decrease in 2011

 

195 MW

 

Net decrease after 2011

 

284 MW

 

Please note that recently some of our customer generators reduced their maximum MW outputs, but those reductions occurred after the cutoff points defined below.

 

Cutoff dates

For model building purposes, we assumed cutoff dates for generation changes to be included in models. In order to include the latest data in the models, cutoff dates correspond to the dates the models were built as follows:

  • 2012 models - October 25, 2010
  • 2016 models - October 25, 2010
  • 2021 models - October 25, 2010
  • 2026 models - October 25, 2010 

It was assumed that if the generator was available as of the cutoff date, it was available for dispatch in that grouping of models.

 

Generation projects schedule

To maintain the schedule needed to complete this Assessment, the models were developed during late 2010 and early 2011. Only those generation projects that qualified to be included in our planning models as of the various cutoff dates, were included in the Assessment models. For generation projects not in service by June 2011, the criterion above resulted in the following proposed generation projects being included in the applicable power flow models:

Plant Name

Zone

Installed capacity increase

Dispatched increase

Assumed in-service

Point Beach #1

4

103 MW

103 MW

Dec 2011

Point Beach #2

4

105 MW

105 MW

Jul 2011

Quilt Block wind farm

3

19.6 MW

19.6 MW

Dec 2012

Glacier Hills wind farm

3

49.8 MW

49.8 MW

Dec 2011

Stoney Brook wind farm

4

19.7 MW

19.7 MW

Mar 2012

EcoMet wind farm

4

20.1 MW

20.1 MW

Dec 2012

Ledge wind farm

4

30.0 MW

30.0 MW

Dec 2012

Lake Breeze wind farm

4

19.6 MW

19.6 MW

Oct 2013

 

 

 

 

 

Net increase by Dec 2011

 

802.4 MW

 

 

Net increase 2011-2020

 

49.6 MW

 

 

*wind farm Installed capacity lists is 20% of total installed capacity

A more comprehensive discussion of proposed generation is provided in Generation Interconnections, including a map showing all of the currently active generation interconnection requests that ATC has received (See Figure PR-9)

 

Generation outside system

The model for the system external to ATC was taken from the most appropriate model included in the MMWG 2010 Series models. The external system interchange was adjusted from the 2010 MMWG Series models to match the latest ATC members’ firm interchange with the exception of the Shoulder 70%, East to West Bias and the West to East Bias models which were built to represent a 3000, 1700 and 700 MW imports into ATC respectively.

 

Generation dispatch

Balancing Authority (Control) area generation was dispatched based on economic dispatch for that Balancing Authority with the exception of the Shoulder 70%, West to East Bias and Light Load models.

 

Line and equipment ratings

We revised line and equipment ratings based on updates to our Substation Equipment and Line Database (SELD). As of April 2011, nearly 76 percent of all ATC lines and 91 percent of ATC transformers have SELD ratings that have been validated. Additionally, nearly 97 percent of ATC lines 100 kV or higher have ratings in SELD that have been validated. Ratings not yet validated in SELD generally are based on the ratings received from the utilities that contributed the facilities to ATC.

 

Project criteria included in all assessment models

All of the models built for the Assessment include revised system topology based on projects that were placed in service in the model year, or were anticipated to be placed in service by June 15 of that year. Refer to Tables PF-1 through PF-4 for projects that were included in the analyses. Please also refer to the Project deficient seasonal models for more discussion about how projects are chosen for inclusion our models.

 

Steady state power flow models

Normal (Category A) Conditions

The load flow models for the 10-Year Assessment are built to include established (pre-contingency) operating procedures to assess system performance under the normal (Category A) conditions as required in the TPL-001-0 Reliability Standard. The relevant operating procedures are generally standing operating procedures that apply for the planning horizon. These procedures include, but are not limited to, normal open points and switched capacitor banks. Normal Open points are assumed to remain normally open in the base cases. Changes in the status of Normally Open points are provided by the system planners that participate in the decision to change the status of a Normally Open point. Switched non-mobile capacitor banks are assumed to be available for use by the system operators, except in the case of planned outages. This availability is represented by modeling these capacitor banks in the discrete adjustment voltage regulating mode.  Mobile capacitor banks are modeled in the base case when there is a known date and location in the planning horizon during which the mobile capacitor bank is planned to be in service.

 

Planned Maintenance and Construction Outages

The load flow models for the 10-Year Assessment are built to include maintenance and construction outages that are planned to occur in planning horizon. These outages are typically conditions that are expected to last for a period of six months or more. The modeled outages are provided by the system planners that participate in the decision to schedule the maintenance or construction outage.

 

Protection Systems

All existing and planned protection systems, including any backup or redundant systems that would be applicable to a given contingency were simulated in the studies and analyses.

 

Control Devices

All existing and planned control devices that would be applicable to a given contingency were simulated in the studies and analyses. These control devices include transformer automatic tap changers, capacitor bank automatic controls, and Distribution Superconducting Magnetic Energy Storage (DSMES) units.

 

Project deficient seasonal models

The load flow models built for the 10-Year Assessment are special models built exclusively for system analyses in the Assessment. Some projects were purposely left out of these models in order to verify system problems and determine which problems worsen over time. We have taken the approach of evaluating subsequent summer peak seasons in each of our annual Assessments to determine the immediacy of needs identified, hence providing a means of prioritization.

 

The 2012, 2016, 2021 and 2026 steady state project deficient summer peak models were developed to evaluate needs, verify findings of the previous year’s Assessment, and confirm that previously identified needs will increase over time. The 2021 and 2026 project deficient models reflect years sufficiently forward in time to determine the need for and assess the performance of larger-scale projects (345-kV lines, for example) that could be expected to be in service in that timeframe.

 

All project seasonal models

After the initial analyses portion of the 10-Year Assessment was completed, “All Project” models were built. The “All Project” models were built with all planned and proposed projects included as well as the majority of the provisional projects. These models are more indicative of the expected system configurations for the three study years. The “All Project” models are more appropriate for internal studies performed by ATC planners throughout the year and for regional models. As part of the 10-Year Assessment, the zone planners perform contingency analyses on each of the “All Project” models. These analyses will verify whether all of the planned, proposed, and provisional projects will resolve issues revealed in the 10-Year Assessment process and will not introduce any new limitations.      

 

Load, dispatch and interchange profiles

Load Sensitivities (2016)

ATC planning explored two sensitivity analyses in our 2011 10-Year Assessment analyses, the minimum (light load) scenario and the west to east bias scenario. The modeling details of these sensitivities are outlined below.

Minimum load scenario (2012)

  • ATC Load:  6,035 MW
    • 2010 forecast collection, scalable loads reduced to 40% of peak + non-scalable loads = 46% of Peak load
  • Total ATC Generation:  5,856 MW
  • Includes all planned and proposed projects to be in-service by 6/15/2012
  • Interchange: Firm interchange only as of 10/25/2010
  • Dispatch: ATC-wide Merit order as of 10/25/2010

West to East Bias scenario (2016, 2021)

  • ATC Peak Load:  9,496 MW
    • 2010 forecast collection, scalable loads reduced to 65% + non-scalable loads = 69% of Peak load as drawn from Operations historical data
  • Total ATC Generation:  9,160 MW
  • Includes all planned and proposed projects to be in-service by 6/15/2016
  • Interchange: ATC net as provided in Operations data -700 MW
  • Dispatch: ATC-wide Merit order as of 10/25/2010
  • Special additions:
    • Wind generation in the ATC footprint dispatched to 45% of Pmax as drawn from Operations historical data,
    • Wind generation west of ATC dispatched to 50% as drawn from Operations historical data,
    • Wind Generation south of ATC dispatched to 55% as drawn from Operations historical data,
    • Minnesota-Wisconsin Export interface (MWEX) loaded to 1400 MW
    • Manitoba Hydro Exports set to 1,350 MW
    • All generation increases were modeled to generation reductions south and east of ATC

Summer peak (2012, 2016, 2021, 2026)

  • We utilized interconnection point load forecasts provided by various distribution companies in 2010 for both real and reactive power components of load. Please refer to the Load Forecast section for further details.
  • Only firm interchange was included in our analyses.
  • Special additions: none

Summer peak 95% QMax (2012, 2016, 2021, 2026)

  • We utilized interconnection point load forecasts provided by various distribution companies in 2010 for both real and reactive power components of load. Please refer to the Load Forecast section for further details.
  • Only firm interchange was included in our analyses.
  • Special additions: Generator QMax reduced to 95%.

Summer peak 90% QMax (2012, 2016, 2021, 2026)

  • We utilized interconnection point load forecasts provided by various distribution companies in 2010 for both real and reactive power components of load. Please refer to the Load Forecast section for further details.
  • Only firm interchange was included in our analyses.
  • Special additions: Generator QMax reduced to 90%.

High load model (2016)

  • We utilized interconnection point load forecasts provided by various distribution companies in 2010. The 2016 high load (or “hot summer”) model was created by increasing load 5 percent above expected summer peak conditions as a proxy for a 90/10 model in order to determine in-service date sensitivity to load growth that is higher or weather that is warmer than forecasted. Please refer to the Load Forecast section for further details.
  • The system external to ATC was taken from the MMWG 2010 Series, 2016 summer model.
  • The external system interchange was adjusted from the 2010 MMWG Series 2016 summer interchange to match latest ATC members’ firm interchange.
  • ATC load forecast increased by 5% above the summer peak load forecast using a constant power factor

Shoulder 70% models (2016, 2021)

  • We utilized interconnection point load forecasts provided by various distribution companies in 2010.
  • The 2016 and 2021shoulder models were created by selectively scaling down loads that generally vary by time-of-day to approximately 70 percent of the summer peak condition. A 70 percent load level was chosen to represent the shoulder model because under this scenario, flows are changing as a result of the Ludington pumping cycle. However, we recognize that loads at individual points will vary under real-time shoulder conditions.
  • The shoulder 70% model included a 3000 MW import into ATC. Firm interchange plus economic transactions up to a 3000 MW import were included.

Shoulder 90% models (2016, 2021)

  • We utilized interconnection point load forecasts provided by various distribution companies in 2010. The 2016 shoulder 90% model was created by decreasing load 10 percent below expected summer peak conditions. Please refer to the Load Forecast section for further details.
  • To simulate a steady state reverse east-west bias power flow, models were developed with 90% load levels, 1700 MW import into ATC, and a 2000 MW transaction from east to west.
  • ATC system biased in an East to West direction.

 

Model years

We started model development for this Assessment by building a system model that represented 2011 summer peak conditions. This 2011 model is referred to as an “as-planned” model because essentially everything in the model is certain to be in service by 2011 summer. This model then was modified to create each of the subsequent Assessment study models including the changes previously described for each model.

 

Computer simulation model years for the 2011 network Assessment analyses were selected in order to meet NERC requirements for a 1-5 year horizon and beyond the 5 year horizon. The years 2012 and 2016 were selected to meet the 1-5 year horizon. The years 2021 and 2026 meet the beyond 5 year horizon.  The years 2012, 2016 and 2021 were chosen to coordinate with the most recently released MMWG models that were available.

 

The 2012, 2016, 2021 and 2026 models were developed to evaluate needs, verify findings of the 2010 Assessment, and confirm that previously identified needs will increase over time. The 2021 and 2026 models reflect years sufficiently forward in time to determine the need for and assess the performance of larger-scale projects (345-kV lines, for example) that could be expected to be in service in that timeframe.

 

Dynamic stability/short-circuit assessment models

ATC conducts transient analyses to evaluate dynamic stability of generators as part of our study of new generation interconnections and voltage stability analysis on portions of the system where severe low voltages are identified. In instances where our stability criteria were not met, remedial projects were devised and included in this Assessment (see System stability).

 

ATC also conducts a short circuit analysis of the entire system on an annual basis or as part of our study of new generation interconnections to evaluate the adequacy of circuit breakers on the transmission system. In instances where short-circuit duties exceeded existing circuit breaker ratings, plans for circuit breaker replacements have been included in this Assessment.

 

Preliminary needs and solution development

Steady state project-deficient needs assessment

System intact and single contingency simulations

ATC performed system intact and single contingency simulations on the 2012, 2016, 2021 and 2026 models. Single contingency simulations include the following: single element (line, transformer, generator, bus and switched shunt) and event-based breaker-to-breaker outages. We run these simulations for summer peak and under the sensitivity situations described above .

Comparison of results vs. Planning Criteria

The models described above are analyzed and compared to our Planning Criteria. Limits that approach or exceed our criteria are then listed in Tables ZS-1 through ZS-4.

Reconciliation of significant changes to power flow results

To reconcile changes in power flow results between Assessments, zone planners run data comparisons to determine if limitations identified in prior Assessments have become more severe, less severe, or have been mitigated. Steps are taken to verify topology and other model changes to ensure that the results are consistent with all of the available information.

Future considerations

In future Assessments, we plan to communicate needs and solicit solution development options to our stakeholders earlier in the process.

Preliminary solution development

New Limitation

If a new limitation is found in the initial screening, the zone planner will take steps to ensure that the limitation is valid, including verification of the power flow model. If the new limitation is within the current five-year timeframe, the zone planner will then check for potential delayability, including investigation of operating guides or other mitigation measures.

 

After all potential mitigation measures for a given limitation or need have been evaluated, system solution options are developed. Potential projects that may resolve identified needs are vetted internally and with our external customers. Each solution option is subject to sufficient evaluation to determine its effect upon the identified limitation. After all discussion and collaboration has concluded, the results for all the solution options evaluation are recorded in a project development document.

 

Cost estimates are developed for solution options that effectively address the identified limitation. After cost information has been obtained, the zone planner selects the most efficient solution option from a cost-benefit standpoint and initiates the project development process by completing the project request form to create a provisional project.  Finally, the project request is processed through ATC’s Project Approval Process.

Repeat Limitation

If a previously identified limitation is found in our initial screening, the zone planner will re-verify that existing solution options address that limitation. If an in-service date or scope change is warranted, updated cost estimates are developed. The project request form is then updated with the revised in-service date, cost, scope, and/or justification. The updated project request form is then resubmitted through ATC’s Project Approval Process.

 

Unspecified Network Project (Placeholder) Process

Unspecified Network Projects are defined as those projects which may shift into the 10-year timeframe as a result of:

  • Changing load forecast,
  • Changes in generation and distribution interconnection projects,
  • Changes in mandatory reliability or renewable portfolio standards, and/or
  • Additional projects that are driven by economic benefits or multiple outage impacts.

Several million dollars were set aside in ATC’s budget in order to address Unspecified Network Projects. ATC’s placeholder process begins with internal discussions to determine how to best serve our customers’ local and regional needs. In these discussions, we collaboratively determine which potential projects may be built or incur costs within the 10-year Assessment period. Projects with a 50 percent probability of occurrence or greater are estimated. The cost/benefit results are discussed, vetted and approved by our AIM Executive committee. After consensus is reached, our capital forecast is updated to include these placeholder dollars.

 

All Projects assessment

After the 10-Year Assessment analysis is completed, models are built that include all planned, proposed, and some provisional projects. These models are called “All Projects” models and are more indicative of the expected system configurations for 2012, 2016, 2021 and 2026 study years. These models are more appropriate for internal planning studies performed throughout the year.

 

As part of the 10-Year Assessment, zone planners perform a contingency analysis on each of the “All Projects” models. The contingency analysis includes systematically removing each line, generator, transformer, switched shunt and modeled bus ties individually to determine the effect on the transmission system. The analysis will verify whether all of the planned, proposed, and provisional projects will resolve issues revealed in the Assessment process.     

 

The zone analysis discussions presented in this Assessment provides a list of reinforcements that are beginning to optimize our reinforcement plans, at least at the one- or maybe two-zone level. Three important questions regarding this plan include the following:

  • How do the reinforcements for all the zones perform together?
  • Does applying a solution in one zone create a problem that was not seen before in another zone?
  • Are some zone solutions redundant when all the solutions are applied to the system?

As we did in the 2010 Assessment, this year we attempted to address the first two questions. We built year 2012, 2016, 2021 and year 2026 models that included reinforcements reflecting our best thoughts on all of the most likely planned, proposed, and provisional projects to address the identified issues. These projects are those identified in the project tables for this Assessment with specific in-service dates. First contingency analysis was performed on these new models, including selected outages on neighboring systems. This analysis showed that the reinforcements in total did indeed deal with the issues identified and did not create any new issues to be resolved. Please refer to the All Projects section for details of our analyses.

 

Stability review & analysis

For system stability analyses methodology and results see the Generator Stability, Voltage Stability and Small Signal Stability sections of the System Stability section.

 

Multiple outage review & analysis

We conduct a variety of multiple outage analyses.  For steady state analyses methodology and results see the Multiple Outage Analysis section. 

 

Documentation

Writing/approval processes

The 10-Year Assessment is written and developed by several contributors. The following steps are performed in order to ensure cohesive, consistent information:

  • Requests are made for the latest financial, environmental, demographics, asset renewal and economics information from other ATC departments.
  • Drafts of each section’s text, figures and tables are compiled for peer review.
  • A comprehensive meeting is held with all Planning and Asset Renewal managers and team leaders in order to review and approve the information.
  • A summary presentation of all Assessment information is reviewed and approved by ATC management.

Once the information has been approved by all parties, the hard copy Summary Report and Zone Summaries are printed and distributed, and the Full Report text is posted at www.atc10yearplan.com.



 
Copyright 2011 American Transmission Company. All Rights Reserved