ROUTING & SITING
    Public outreach
Siting process
New right-of-way
Existing right-of-way
  RELATED RESOURCES
 
Table RS-1 -- Projects requiring new ROW (61k pdf)
Table RS-2 -- Environmental Screening Information (72k pdf)
Exhibit RS-1 -- 18th Road - Chandler (1.3M pdf)
Exhibit RS-2 -- Clear Lake - Woodmin (1.5M pdf)
Exhibit RS-3 -- Dunn Road - Egg Harbor (1.8M pdf)
Exhibit RS-4 -- Fairwater - Mackford Prairie (1.0M pdf)
Exhibit RS-5 -- Hubbard - East Beaver Dam( 1.8M pdf)
Exhibit RS-6 -- Lake Delton - Birchwood (1.4M pdf)
Exhibit RS-7 -- North Lake Geneva - South Lake Geneva (1.2M pdf)
Exhibit RS-8 -- Rockdale - West Middleton (Cardinal) (2.5M pdf)
Exhibit RS-9 -- Shoto - Custer (1.7M pdf)
Exhibit RS-10 -- Spring Valley-Twin Lakes - South Lake Geneva (1.7M pdf)
Exhibit RS-11 -- Badger Coulee (2.5M pdf)
Exhibit RS-12 -- Dubuque-Spring Green-Cardinal (2.0M pdf)
Exhibit RS-13 -- Barnhart-Branch River (Erdman-Barnhart) (1.4M pdf)
Exhibit RS-14 -- West Milwaukee County Reliability Project (Milwaukee County T-D) (1.5M pdf)
Exhibit RS-15 -- Pleasant Prairie-Zione Energy Center (1.3M pdf)
NEW RIGHT-OF-WAY PDF of Current Page
 

In addition, in siting and evaluating potential routes for transmission lines, consideration must be given to sensitive areas, which generally involve public or environmental issues. Information about sensitive areas can be found in Table RS-2

(72k pdf) .

 

When new transmission line projects involve new rights-of-way, we gather environmental screening information. The environmental assessments provided in this section are high-level and not nearly the level of investigation that will accompany a permit application to construct transmission facilities.

 

Table RS-1 (61k pdf) lists the new transmission lines requiring new right-of-way and whether high-level environmental screening information is provided in this report or can be found in application materials already filed with the Public Service Commission.

 

Table RS-2 (72k pdf) provides environmental screening information for the lines listed in Table RS-1 (61k pdf). Exhibits RS-1 through RS-15 (8.6M pdf) identify the approximate end-points and study areas for each project for which high-level environmental screening information is provided.



 