PROJECTS
    Classifications
Completed since 2010
New in 2011
Under construction
Pending approval
Costs
Generation Interconnections
T-D Interconnections
  RELATED RESOURCES
 
 
Table PR-27 -- Generator Requests now in service (80k pdf)

Table PR-28 -- Projects in Generation Queue (142k pdf)

Table PR-29 -- Withdrawn from Generation Queue (108k pdf)

Figure PR-9 -- Generation Interconnection Requests (116k pdf)
Figure PR-10 -- New Generation Queue  by Technology (35k pdf)
GENERATION INTERCONNECTIONS - Updated November 2007 PDF of Current Page
 

The size and location of new or expanded power plants can have significant impacts on the transmission system. These impacts can range from very positive (adding voltage support in a weak area of the system) to very negative (aggravating loading problems and/or causing generator instability). Information on the status, as of July 1, 2007, of ATC’s portion of the Midwest Independent System Operator generation interconnection queue is provided in this section. There continues to be significant activity in ATC’s portion of this queue, ranging from newly proposed generation projects to cancellation of previously proposed generation projects.

 

There are two key aspects in determining the total impacts a proposed new generator may have on the transmission system:

  • impacts of interconnecting the new generator to the transmission system and
  • impacts of using the transmission system to deliver power from the new generator.

 Per the Midwest ISO Attachment X process, interconnection impacts are assessed using up to three interconnection studies. The first study, called a feasibility study, includes a determination of thermal overload or voltage level impacts created by the new generator. The second study, called an impact study, includes a determination of whether the proposed generator and other nearby generators will remain stable under various disturbance situations, like line trips and equipment failures. It also includes a fault study analysis to determine whether existing system equipment can accommodate the increased short circuit fault duty caused by the new generator. It also identifies solutions for any thermal, stability or fault duty problems. If problems are identified in the impact study, a third study, called a facility study, is conducted to settle on solutions and provide cost and time estimates for construction. Delivery impacts are assessed during the interconnection study process using the Midwest ISO deliverability methodology, which determines whether a new generator is deliverable to the Midwest ISO Day 2 market and to what percent if not wholly deliverable. Whatever portion of the new generator that is deliverable may then be used as a Network Resource by Network Customers through the Midwest ISO’s Module E Resource Adequacy procedures.

 

The results of the interconnection studies are needed to develop a comprehensive picture of the transmission facilities that will be required for a proposed generator. This is why we included in our Assessment models those proposed generators for which interconnection studies have been completed.

 

The first portion of this section provides the status of the generation queue within our service territory. The second portion of this section describes the transmission system additions associated with various proposed generation projects for which final interconnection studies have been completed. The third portion of this section describes some of the implications associated with interconnecting generation at various locations within our service territory.

 

ATC Generation Queue

Since ATC’s inception, ten new generators have gone into service and one uprate to an existing generator has been completed, totaling 2,780 MW. These generators are shown in Table PR-27.

 

Table PR-28 lists the proposed generators in the generation queue for our service territory as of July 1, 2007. This table lists each proposed generation project and summarizes them by zone and MW amount. These proposed projects also are shown by approximate location in Figure PR-9. As shown, the total capacity of proposed generators in the queue is 5,213.5 MW. Of that proposed capacity, 44 percent reflects new coal units; wind units reflect 43 percent; combined cycle (natural gas) units reflect 12 percent; and the remaining 1 percent is comprised of simple cycle (natural gas) turbines (see Figure PR-10). Of this generation, 37 percent is proposed in Zone 5, 23 percent in Zone 3, 22 percent in Zone 4, 12 percent in Zone 1, and 6 percent in Zone 2.

 

The developer’s projected in-service date listed in Table PR-28 is the last official commercial operation in-service date provided by the developer for that request. A developer may, per the Midwest ISO’s Attachment X procedures, suspend their Interconnection Agreement which may delay the project. A developer is not required to update their official in-service date as part of this suspension.

 

The following requests have been suspended:

  • G282 – 99 MW wind farm, Line X-14 in Lafayette County, Wisconsin
  • G366 – 80 MW wind farm, Friesland Substation in Columbia County, Wisconsin
  • G376 – 160 MW wind farm, Line X-4 in Green Lake County, Wisconsin
  • G384 – 99 MW wind farm, Line Y-51 in Manitowoc County, Wisconsin
  • G427 – 98 MW wind farm, Cypress Substation in Fond du Lac County, Wisconsin
  • G483 – 50 MW wind farm, Line Y-33 in Green County, Wisconsin
  • G546 – 100 MW wind farm, Line 6541 in Walworth County, Wisconsin

 

Generation interconnection requests previously in the generation queue, which have been cancelled or removed from the queue since January 31, 2007 (because the developer withdrew the request or missed contractual milestones), are summarized in Table PR-29.

 

Link to publicly posted generation queue: http://oasis.midwestiso.org/documents/ATC/Cluster_8_Queue.html

 

Transmission associated with proposed generation interconnections

Prior to the start of the MISO Day 2 Market, transmission service for new generators was handled separately through an OASIS transmission service request(s). For generators listed below that had studies completed prior to Day 2 start-up, system reinforcements were identified through both generator interconnection and transmission service studies.

 

Implications of generation development

Availability of fuel, water and transmission interconnections are among the key aspects to be considered when siting generation.

 

From a transmission perspective, the ability of the transmission system to accommodate new generation is a function of stability, power flow and short circuit analyses. For certain generation technologies, harmonics and voltage fluctuations may need to be considered as well. In most instances, new generation will require certain transmission system reinforcements to interconnect and deliver the generation output. In a few specific instances, new generation can be beneficial to the transmission system, perhaps even deferring or eliminating the need for transmission reinforcements that would be necessary absent the new generation. The ability of generation to defer or eliminate the need for transmission reinforcements also can be a function of the generation location, number of generators and/or expected generator capacity factor.

 

In this section, a very general zone-by-zone evaluation of the likelihood of needing or deferring transmission reinforcements for various generator locations is provided. The purpose of these evaluations is to provide a very cursory indication to the generation market of the likely magnitude of the impact and the transmission reinforcements that would likely be needed by general location.

Zone 1

Within Zone 1, generation has been proposed in various locations, but most of the proposals have involved generation located in the vicinity of the 345-kV infrastructure. Based on studies that we have conducted for proposed generation interconnections and transmission service from this area to date, some transmission reinforcements are likely to be required for any significant (>100 MW) generation development. The extent and nature of the reinforcements largely would be a function of where the power from the generation is to be delivered.

 

The northern portion of Zone 1, the Rhinelander Loop, is a potential candidate for moderate-sized (up to 150 MW, depending on location) generation development, provided generator stability can be maintained, and provided it can be located in the northern portion of the Loop. Whether this generation would be cost-effective as a transmission-deferral mechanism would depend on a number of factors. The need for additional reinforcements outside of the Loop would be a function of where the power from the generation is to be delivered.

 

The infrastructure in the southern portion of Zone 1 consists of five 138-kV lines and several 69-kV lines. Only smaller generation projects (<25 MW) could be accommodated with minimal transmission reinforcements. The existing infrastructure in this portion of Zone 1 is not suitable for any significant generation development.

 

Zone 1 completed generation studies:

Request

Size

Type

County, State

GIC044

500 MW

Coal

Marathon County, Wisconsin

G522

550 MW

Coal

Portage County, Wisconsin

G523

550 MW

Coal

Marathon County, Wisconsin

G588

55/60 MW

Combustion turbine

Wood County, Wisconsin

 

Zone 2

We have completed studies of three generation interconnection requests in Zone 2. Although these three requests are no longer active in the queue, they have helped us build a base of knowledge similar to what we have in other zones relating to likely generation interconnection impacts.

 

The most logical generation locations from a transmission infrastructure standpoint would be near the existing Presque Isle Power Plant or the Plains Substation due to the number of 138 kV lines emanating from these substations. However, any significant generation development at or near the Presque Isle Power Plant likely would require transmission reinforcements or additions due to the existing stability and thermal issues there. The completion of the Northern Umbrella Plan, however, will result in a much more robust 138-kV network at Plains Substation that could accommodate a reasonable amount of generation in the future at or near Plains.

 

It is likely that given the scarcity of 138-kV infrastructure in the Upper Peninsula there are virtually no other locations in Zone 2 that are ideal candidates for significant generation development. The MISO generation interconnection queue contains two proposed wind farms for Zone 2 totaling 320 MW. The studies for these requests are still in progress and required transmission reinforcements have not yet been identified. 

There are areas in Zone 2, such as on the western end of the Upper Peninsula, which are or will be in need of transmission reinforcements where smaller generation projects could be beneficial in terms of deferring transmission expenditures. The allowable capacity of such generation would depend on the location. However, other potential impacts (stability, fault duties) would need to be evaluated on a location-by-location basis.

 

Zone 2 completed generation studies:

Request

Size

Type

County, State

G567-568

165 or 300 MW

Coal

Delta County, Michigan

G583

19 MW

Biomass

Ontonagon, Michigan

 

Zone 3

In Zone 3, generation has been proposed in various locations, but over half have been in the southern-most counties in Zone 3. Generation could be beneficial in a few areas depending on the capacity of such generation and the exact location.

 

We are projecting that the Dane County electric system could become subject to thermal overloads, low voltages or voltage collapse, significant load shed risk, and restrictions on power imports into the county as early as 2011. We believe that extending the 345-kV network to the west side of the Madison metropolitan area, coupled with additional 138-kV reinforcements within the city and reactive support will resolve these issues over the long term.

 

Sauk County, though we are currently reinforcing the system, is projected to need additional transmission reinforcements in the future to ensure reliable operation. Smaller-scale generation (< 100 MW) in certain locations could be beneficial to improving the voltage profile in the area and potentially deferring transmission reinforcements. Stability analysis would need to be conducted to ensure stable operation of such generation.

 

Similarly, the southeast portion of Zone 3 is heavily loaded and will require transmission reinforcements in the future to ensure reliable operation. Small-scale generation in certain locations could be beneficial to changing power flow patterns and improving the voltage profile in the area.

 

Zone 3 completed generation studies:

Request

Size

Type

County, State

G281

130 MW

Wind

Green County, Wisconsin

G282

99 MW

Wind

Lafayette County, Wisconsin

G338

54 MW

Wind

Dodge County, Wisconsin

G366

80 MW

Wind

Columbia County, Wisconsin

G371

100 MW

Wind

Columbia County, Wisconsin

G483

50 MW

Wind

Green County, Wisconsin

G527

280 MW

Coal

Grant County, Wisconsin

G528

550 MW

Coal

Columbia County, Wisconsin

G546

100 MW

Wind

Walworth County, Wisconsin

G550

24 MW

Simple cycle/gas

Jefferson County, Wisconsin

G553

280 MW

Coal

Columbia County, Wisconsin

G706

99 MW

Wind

Columbia County, Wisconsin

G724

99 MW

Wind

Dane County, Wisconsin

G747

99 MW

Wind

Rock County, Wisconsin

G749

99 MW

Wind

Lafayette County, Wisconsin

 

Zone 4

Generation has been proposed in various locations in Zone 4. Generation could be beneficial in a few areas depending on the capacity of such generation and exact location. Given the nature of the issues in Zone 4, however, it is unlikely that new generation in Zone 4 will significantly alter the need for the major transmission reinforcements contemplated in that zone.

 

One area where generation could defer the need for transmission reinforcements is in Door County, provided such generation is small-scale (< 50 MW) and appropriately located. Currently, the northern portion of the county is served radially, and electric service is subject to interruption for the loss of the single 69-kV line serving the area. The voltage profile in Door County is projected to precipitate the need for reinforcements in the future. Small-scale generation potentially could defer certain of these reinforcements.

 

One area in Zone 4 that cannot accommodate any additional generation without significant transmission reinforcements is the area around the Point Beach and Kewaunee nuclear plants. In this area, existing transmission lines have little excess capacity. As the system evolves, stability margins at those plants may become a concern. Additional generation may require transmission reinforcements to meet our stability criteria.

 

Zone 4 completed generation studies:

Request

Size

Type

County, State

G240

55 MW

Steam

Manitowoc County, Wisconsin

G338

54 MW

Wind

Dodge County, Wisconsin

G353-4

160 MW

Wind

Fond du Lac County, Wisconsin

G368

200 MW

Wind

Fond du Lac County, Wisconsin

G376

160 MW

Wind

Green County, Wisconsin

G384

99 MW

Wind

Manitowoc County, Wisconsin

G410

99 MW

Wind

Kewaunee County, Wisconsin

G421

50 MW

Wind

Brown County, Wisconsin

G427

98 MW

Wind

Fond du Lac County, Wisconsin

G486

10.5 MW

Wind

Manitowoc County, Wisconsin

G507

98 MW

Wind

Fond du Lac County, Wisconsin

G590

98 MW

Wind

Calumet County, Wisconsin

G611

99 MW

Wind

Calumet County, Wisconsin

 

Zone 5

Two major generation additions have been proposed in Zone 5. The first addition is at Port Washington Power Plant, which has been approved by the Public Service Commission of Wisconsin. Two groups of units will be installed. The first phase went in service in 2005 and the second phase is under construction to go in service in 2008. Rebuilding existing transmission lines in the Port Washington area is required to support this new generation. In order to accommodate the two units of generation at Port Washington, the two Port Washington–Rangeline 138-kV lines and the three Port Washington–Saukville 138-kV lines were rebuilt in 2005. The final project is rebuilding the Saukville–Pleasant Valley–Arthur Road–St. Lawrence 138-kV line. This line rebuild project will start in fall 2007 and be completed before June 2008 at a cost of approximately $10 million.

 

The other site for new generation is the Oak Creek Power Plant. The PSCW has approved two units at the Oak Creek Power Plant, with the first unit going into service in 2009 and the second unit in 2010.

 

Studies of other proposed generation projects that are no longer in the generation queue indicate that additional generation in certain areas of Zone 5 would pose stability problems. In particular, larger-scale generation interconnecting to the 345-kV network could pose stability issues.

 

Smaller-scale generation in certain locations in Washington and Waukesha counties potentially could be accommodated without the need for transmission reinforcements if located appropriately.

 

 

Zone 5 completed generation studies:

Request

Size

Type

County, State

G051

1950 MW

Coal/steam

Milwaukee County, Wisconsin

GIC027

1200 MW

Combined cycle

Ozaukee County, Wisconsin

G510

90 MW

Combined cycle

Ozaukee County, Wisconsin

 

 

 

 



 
Copyright 2011 American Transmission Company. All Rights Reserved