Projects completed since last report
Transmission projects significantly affecting the system performance that have been completed since the 2018 Assessment was issued in October 2018, include:
System Addition | Planning Zone |
---|---|
Cranberry Substation 11-kV, 10.4 MVAR inductor bank | 1 |
Plover SS, Distribution Interconnection (DIC) - replace transformers | 1 |
Sherman Street SS, DIC - replace high side circuit switcher | 1 |
North Madison - Briggs Road 345-kV line | 1, 3 |
Iron Grove: 138-kV, 15 MVAR inductor bank | 2 |
J703 Huron SS, generator interconnection (GIC) facilities | 2 |
J704/J711 GIC - network upgrades | 2 |
J704/J711 GIC- Silver River SS-interconnection and network upgrades | 2 |
Plains - Arnold 138-kV uprate | 2 |
Winona Substation: 138-kV, 8 MVAR inductor bank | 2 |
Baraboo SS, bus uprate and RTU replacement | 3 |
Construct Edgerton transmission to distribution (T-D) interconnection 138-KV | 3 |
Darlington SS, DIC - replace transformer and construct new control house | 3 |
J390: Kittyhawk Substation, new generation to transmission (G-T) interconnection | 3 |
J395: Darlington - North Monroe 138-kV line X-49, uprate | 3 |
Paddock - NW Beloit 138-kV line X-53, install series reactor | 3 |
Tripp Rd Substation, breaker installation | 3 |
Williams Bay Substation: loop X-44 in and out | 3 |
Construct a new 138/69-kV substation on Spring Valley - North Lake Geneva 138-kV circuit | 3 & 5 |
Construct a new 69-kV circuit from Twin Lakes to the new substation | 3 & 5 |
Twin Lakes - Katzenberg 69-kV rebuild Y-102 | 3 & 5 |
Bay Lake: Morgan Substation - reconfigure and expand 345-kV and 138-kV switch yards | 4 |
Bay Lake: North Appleton - Morgan 138-kV line construction | 4 |
City Limits 138-kV bus reconductor | 4 |
Depere - Glory Rd 138-kV overhead line rebuild | 4 |
Forest Junction 138-kV Substation: install redundant bus differential | 4 |
Highway V Substation: Install 138-kV breakers and 69-kV circuit switchers on 138/69-kV transformers | 4 |
Lost Dauphin - Red Maple 138-kV line uprate Q-147 | 4 |
Oak St SS, DIC - replace transformer | 4 |
Plymouth 4 Substation, breaker installation | 4 |
West Marinette Substation: add high side protection to 138/69-kV transformers | 4 |
Berryville SS, DIC - add second transformer | 5 |
Mukwonago Substation: install line breaker on line 671K61 | 5 |
Somers Substation: loop Racine - Kenosha 138-kV line 1651 in and out | 5 |