Projects completed since last report
Transmission projects significantly affecting the system performance that have been completed since the 2016 Assessment was issued in October 2016, include:
Project Name | Zone |
---|---|
ACEC Dellwood Substation: Install line breakers to sectionalize Y-146 | 1 |
Tomahawk Substation: Install bus tie breaker to sectionalize | 1 |
Construct Fairwater-Mackford Prairie 69-kV line | 1 |
Reconfigure the North Randolph-Ripon 69-kV line to form a second Ripon-Metomen 69-kV line and retire the circuit between Metomen and the Mackford Prairie tap | 1 |
Zone 2 switching initiative | 2 |
Bay Lake: Benson Lake Substation -- Construct new 138-kV substation and install 150 Mvar SVC (near Amberg Substation) | 2 |
Stagecoach - Wick Drive 69-kV line rebuild Y-62 | 3 |
Brick Church Substation: Remove breaker 1532-S current transformer | 3 |
West Middleton-Stage Coach 69-kV uprate 6927, short term fix | 3 |
University/Whitewater line reconfiguration | 3 |
Red Bird Substation: Tap line N239 | 3 |
J384: Cooney - Summit 138-kV line uprate 6431 | 3 |
Colley Road-Brick Church 69-kV rebuild Y-32 | 3 |
Browntown 69-kV Bus Rerate | 3 |
Retap Colley Rd 138/69-kV T31 current transformers | 3 |
Pulliam - Glory Road 138-kV line conversion K-115 | 4 |
Pulliam Substation: Install a new 138/69-kV transformer | 4 |
Beardsley St. Substation: Install 3 69-kV line breakers to sectionalize 69-kV circuit J-10 | 4 |
Bay Lake: Morgan - Stiles 138-kV circuit de-bifurcate to form 2 separate 138-kV lines | 4 |
Canal Substation: Install 138-kV breakers on 138/69-kV transformers | 4 |
Canal Substation: Install redundant bus differentials on 138-kV buses | 4 |
Esker View Substation: loop LYNG11 in and out | 4 |
Forest Junction 138-kV Substation: Install redundant bus differential | 4 |
Oak Creek-Pennsylvania 138-kV line uprate 837 | 5 |
Bain - Albers 138-kV line uprate 63143 | 5 |