Plans and proposals
For planning purposes, we divide our service area into five zones representing distinct geographic or usage areas. Within each zone, we compile and assess the transmission system needs.
Project classifications
Within each zone, we have recommended network and asset renewal projects to address system limitations. The network projects are classified into one of three possible categories – Planned, Proposed or Provisional – depending upon the stage a project may be in. These categories are consistent with those used by MISO.
Planned | Proposed | Provisional | |
---|---|---|---|
Status of ATC planning activities | Studies complete | Studies not complete | Studies not complete |
Application for regulatory approval | Application pending or issued | None | None |
Project status | Project in construction planning phase or under construction | Project identified as preferred alternative | Placeholder project; not necessarily a preferred project alternative |
System solution included in generation interconnection power flow models | Project included | Project not included | Project not included |