Projects completed since last report
Transmission projects significantly affecting the system performance that have been completed since the 2013 Assessment was issued in October 2013, include:
Project Name | Zone |
---|---|
Uprate Ripon-Northwest Ripon 69-kV line Y-93 | 1 |
Omro - Berlin 69-kV line rebuild Y-80 | 1 |
Chaffee Creek - ACEC Coloma Tap 69-kV line rebuild Y-18 | 1 |
Castle Rock-Mckenna 69-kV line uprate Y-47 | 1 |
Rebuild M38-Atlantic 69-kV line | 2 |
Energize Hiawatha-Indian Lake at 138 kV | 2 |
Construct Old Mead Rd-Chandler double circuit 138-kV lines and operate at 138/69 | 2 |
Construct Old Mead Rd 138/69-kV Substation and install one 138/69-kV transformer | 2 |
Install 2-4.08 Mvar 69-kV capacitor banks at Old Mead Rd | 2 |
West Middleton - West Towne 69-kV line rebuild 6997 | 3 |
Install 1-8.16 Mvar capacitor bank at Boscobel 69-kV Substation and upgrade existing 5.4 Mvar bank with an 8.16 Mvar bank | 3 |
Paddock - Shaw 69-kV line rebuild Y-54 | 3 |
Paddock - Town Line Road 138-kV single circuit rebuild X-39 | 3 |
Portage Substation: Install redundant bus differentials on 138-kV buses | 3 |
Manrap - Custer 69-kV line uprate Y-MRP11 | 4 |
North Fond Du Lac - Metomen 69-kV line uprate Y-27 | 4 |
Rebuild Pleasant Prairie 345-kV bus | 5 |
Construct Pleasant Prairie-Zion Energy Center 345-kV line | 5 |
Racine - St. Rita 138-kV line uprate 8531 | 5 |