2013

10-Year
Assessment

Projects completed since last report

Transmission projects significantly affecting the system performance that have been completed since the 2012 Assessment was issued in October 2012, include:

Project NameZone
Relocate Engadine 69-kV load2
Straits Substation: Install redundant bus differentials on 138-kV buses2
Install 2-16.33 Mvar 69-kV capacitor banks at Nine Springs Substation3
Uprate Fitchburg-Nine Springs 69-kV and Royster-Pflaum 69-kV lines and move AGA load to the Royster-Femrite 69-kV line3
Construct 345-kV line from Rockdale to Cardinal3
Construct a 345-kV bus and install a 345/138 kV 500 MVA transformer at Cardinal Substation3
Christiana Substation: Install redundant bus differentials on 138-kV buses3
Rockdale substation: Install redundant bus differentials on 345-kV and 138-kV buses3
As of August 1, 2013