Michigan’s Upper Peninsula and Northern Wisconsin
Zone 2
Transmission system limitations in Zone 2
There are several potential transmission system performance issues in Zone 2, including limited ability to import or export power, potential generator instability and low and high system voltages. Potential overloads that are a result of multiple contingency planning events will continue to be monitored. The most severe limitations are expected to occur during both peak and off‑peak periods.
Electricity usage
Zone 2 typically experiences peak electric demand during both the summer and winter months. Ore mining and paper mills are the largest electricity users in the zone.
Electric load is forecasted to increase by 0.2 percent annually through 2030. Also, locally generated electricity is declining in the area with smaller, coal‑fired generators most at risk. This includes generation owned by industry, municipalities and utilities.
Transmission projects in Zone 2
The most notable planned, proposed, and provisional network / asset-renewal projects in Zone 2 are listed below – along with their projected year of completion and the factors driving the need for the projects.
The recent installation of inductor banks in the western U.P. have successfully mitigated issues with high voltages during lighter load periods. ATC completed Zone 2 projects that provided new interconnection facilities at Huron and Silver River substations for the new J703 and J704 generation. These new Reciprocating Internal Combustion Engine (RICE) generating plants are important power sources in the U.P. to ensure reliability after the recent retirement of the Presque Isle Power Plant.
Zone 2 includes the counties of:
- Alger , Mich.
- Baraga , Mich.
- Chippewa , Mich.
- Delta , Mich.
- Dickinson , Mich.
- Florence , Wis.
- Forest (N) , Wis.
- Gogebic (E) , Mich.
- Houghton , Mich.
- Iron , Mich.
- Keweenaw , Mich.
- Luce , Mich.
- Mackinac , Mich.
- Marinette (N) , Wis.
- Marquette , Mich.
- Menonminee (N) , Mich.
- Ontonagon (E) , Mich.
- Schoolcraft , Mich.
- Vilas (N) , Wis.
Zone 2 Planned Projects
Project Description | Project # | In-service year | Need driver |
---|---|---|---|
Mackinac–McGulpin 138-kV line (9901 and 9903), submarine cable replacement | 1 | 2021 | Asset Renewal |
Atlantic SS, 138/69-kV Bus Reconfiguration and Transformer Addition | 2 | 2022 | Operational Flexibility |
Presque Isle–Tilden 138-kV Line, Loop and Uprate | 3 | 2022 | Reliability |
NLKG31 Tap–Greenstone 138-kV Line, Construct New Transmission Line | 4 | 2022 | Condition and T-D Interconnection |
Tilden SS, Control House Replacement and Breaker & Relay Asset Renewal | 5 | 2023 | Asset Renewal |
J849, Chandler SS Generator Interconnection Facilities and Network Upgrades | 6 | 2023 | G-T Interconnection |
Winona–Atlantic 69kV (Winona69), rebuild | 8 | 2024 | Reliability |
Zone 2 Proposed Projects
Project Description | Project # | In-service year | Need driver |
---|---|---|---|
Marquette County Reactive Power Project | 7 | 2024 | Reliability |
Zone 2 Provisional Projects
Project Description | Project # | In-service year | Need driver |
---|---|---|---|
Empire SS, Control House Replacement and Breaker & Relay Asset Renewal | 9 | 2024 | Asset renewal |
Munising Area Reactive Power Project | 10 | 2024 | Reliability |